procurement and trade agreements: a practical perspective on cfta and ceta

Spotlight On Legal Risk - The Procurement School

Each New Year is a time to reflect. In 2017 at least two changes occurred that affect supply chain practices. On July 1 the Canadian Free Trade Agreement (CFTA) and on September 21 the Canada-European Union Comprehensive Economic and Trade Agreement (CETA) came into force. Both trade agreements have a significant impact on procurement in the public and broader sectors.

If your organization is required to comply with these trade agreements and has not yet made the necessary procedural, practice or document changes, 2018 is the year to ensure compliance. This article offers some practical considerations for organizations that are required to comply with these trade agreements.

Limited tendering

Single and sole source lists and non-competitive approval forms, both part of most organizations’ procurement toolkits, now require some review and changes. These exceptions and exemptions, now collectively referred to as limited tendering, have changed substantively.
One notable change that will require unpacking and reflects challenges faced in IT procurement is to allow limited tendering if a change of supplier for additional goods or services cannot be made for economic or technical reasons (such as requirements of interchangeability or interoperability with items procured under the initial procurement) and would cause significant inconvenience or substantial duplication of costs.
Additionally, organizations should be prepared to engage in relatively more competitive processes for services by licensed professionals as the list of those professionals in the CFTA non-application provisions has decreased from the Agreement on Internal Trade.

Use of prior experience

The use of prior experience as a routine evaluative requirement in procurement documentation should be scrutinized. In establishing conditions for participation, consideration must now be given to whether the prior experience is essential to meet procurement requirements.

Technical standards

The internal technical standards that organizations have been using for prescribing technical specifications for goods or services being procured should be examined. In keeping with the principles of non-discrimination, the trade agreements have somewhat curtailed the use of internal technical standards and instead focus on documentation approved by recognized bodies and international standards if they exist, otherwise on national technical regulations.

Notices and posting award

One area many organizations have addressed is the revision of pre-release notices and post-award publications. Some electronic tendering systems have made this practice easier by providing templates to enable compliance. Alternatively, the applicable provisions of the trade agreements read as an easy-to-follow checklist, however, care should be given as CFTA and CETA are not entirely aligned. New is the requirement to include whether the procurement will involve negotiation or electronic auction.

Prequalification

While the practice of selecting prequalified suppliers, such as vendor of record and supplier lists, continues to be supported, some details for managing these everyday practices have changed. Organizations should review whether certain requirements to allow suppliers to be added to the list at a later date are addressed and the exceptions for the same.

Low bidding

To address a concern in a competitive marketplace, a refreshed approach in dealing with low bids should be considered. With a new price verification protocol in place, if a low bid is received, an organization may verify with the supplier that it satisfies the conditions for participation and is capable of fulfilling the terms of the contract.

Supplier debrief

An adjustment to debrief processes to support more detailed disclosure requirements is needed. In addition to providing reasons why a tender was not selected, organizations are now required to include the relative advantages of the successful supplier’s tender. This comparative approach adds a different dimension to the debrief process and becomes even more complex when balancing the need for disclosure with the requirement for confidentiality of supplier information. Developing a debrief manual or adjusting existing documentation may be helpful.

*****

While the current environment has necessitated a number of immediate changes, other areas will continue to unfold. Keep your eyes open for developments regarding a single point of contact for electronic notices and a formal review body for the escalation and resolution of supplier disputes.

These new obligations can provide an opportunity for updating procurement procedures, practices and documentation. Many approaches are available that recognize the fiscal pressures under which public sector entities operate, optimize value for money and mitigate risk associated with non-compliance. We suggest that 2018 be the year for trade agreement compliance.

This article first appeared in B2B Magazine February 2018

Debby Shapero Propp is a commercial lawyer with a focus on supply chain, technology and health law, providing practical legal and educational services in the private, public and broader public sectors. Debby has implemented the CFTA and CETA procurement obligations and changes in both procedures and supply chain documentation. She has authored numerous articles and regularly speaks and teaches across Canada. For more information see www.shaperopropp.ca

Sharon Rubinstein is the President and lead consultant for Rubinstein & Associates Inc, a procurement consultancy focused in the public and broader public sectors. Sharon is both a procurement specialist and project manager, focusing on the delivery of complex, strategic procurement projects, as well as the development of customized procurement tools and process improvements to enable organizational effectiveness.

For more information about Sharon, you can visit her on Linked In or contact her directly at [email protected].

Readers are cautioned not to rely upon this article as legal advice nor as an exhaustive discussion of the topic or case.  For any particular legal problem, seek advice directly from your lawyer or in-house counsel.  All dates, contact information and website addresses were current at the time of original publication. 

1. We note that on certain matters these trade agreements are not aligned with each other.

Disclaimer: The views and opinions expressed in this article are those of the Subject Matter Experts and do not necessarily reflect the official policy or position of The Procurement School.

0 thoughts on “procurement and trade agreements: a practical perspective on cfta and ceta

    • Maureen Sullivan, President of NECI says:

      Hi Donna,

      Thanks for the great question!

      I believe the author is referring to Article 515 (6) of CFTA and 19.14(6) of CETA, which states “If a procuring entity receives a tender from a supplier with a price that is abnormally lower than the prices in other submitted tenders, it may verify with the supplier that it satisfies the conditions for participation and is capable of fulfilling the terms of the contract.”

      This is the ‘price verification protocol’ that she refers to.

      I hope this answers your question.

  • Candace McIntosh says:

    Great article, thank you! How should we treat secondary procurements off an established (prequalified) suppliers list? If the initial procurement aligned with trade law obligations, must the individual secondary procurements made from the list also follow trade law (or did the initial procurement already cover this)?

  • Maureen Sullivan says:

    Great question Candace, and not an easy answer. The trade agreements have specific requirements, including continuous advertising of the opportunity to get on the list, and including a description of how the list will be used. If you are following these protocols you should be fine. If however the list is set up by another entity, you will not be compliant with your own organization’s obligation to run a ‘fair, open and transparent’ competitive process. Best to seek legal advice if you have doubts – better to read a case than be a case!

  • Where does the agreements discuss how many days a Request for Pre-qualification needs to be in the market. When issuing tenders to the successful invitational pre-qual list, do you still need to follow the 40 day rule of thumb (minus days for each criteria set out). Is there minus days for tenders in the market because you did a pre-qual first?

  • Damian Jeganathan says:

    We are a public sector entity and we are partnering with two other organisations on a project. One is a public entity like ours and other a private entity. Do we have say in the tendering process according to CFTA/CETA. Can the private partner conduct the procurement process outside of our policies and procedures?

    • Maureen Sullivan, President of NECI says:

      Hi Damian,

      This is a pretty specific question that we don’t really get into in our training; however, our instructor Lise who operates “Patry Law” out of Ottawa might be able to assist you. You can call her at +1 (613) 601-6333. We hope this helps.

      You can also check out Lise’s profile on our website’s “About” page to learn more about her.

Leave a Reply

Your email address will not be published. Required fields are marked *

You may use these HTML tags and attributes:

<a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <s> <strike> <strong>